Electrical Division
Executive Engineers
- Sri. K. Viswanath
- Sri. M. Murali Prakash
Assistant Executive Engineers
- Sri. K. Ravichandran
- Sri. V. Manickavasagam
The Up gradation of 11 kV supply and revamping the existing 11 kV distribution system are the best achievement in this campus for more reliability and better regulation of power supply.
UPGRADATION OF SUPPLY SYSTEM FROM 11 KV to 33 KV
Erection of 33 / 11 KV SubstationClient
*
IIT Madras
Contractor
*
Siemens Ltd., Chennai
Amount
*
Rs. 242 Lakhs
Erection of 33 / 11 KV Substation
Supply, Erection, Testing and Commissioning of
- 2 x 5 MVA 33 / 11 KV Power Transformers
- 33 KV 7 Panel VCB for TNEB RMU
- 33 KV 6 Panel VCB for IIT side
- 11 KV 11 Panel VCB for feeders
- Laying of 33 KV & 11 KV HT XLPE UG cable (0.3 / 3.2 km)
Revamping of 11 KV Distribution System
Client
*
IIT Madras
Contractor
*
BSES LTd., Chennai
Amount
*
Rs. 82 Lakhs
Major Scope of Work
Supply, Erection, Testing and Commissioning of<85><85>
- Construction of substation building (2 nos.)
- 3 x 250 KVA 11 / 433 KV Distribution Transformers
- 11 KV 4 Panel VCB
- 11 KV 3 Panel VCB
- LT Panels
- Laying of 11 KV XLPE UG Cable (2.5 km)